The general contractor has, this week, received prices from three other electrical subcontractors for the Child Care Center Renovation. As mentioned in previous entries, the electrical subcontractor's price jumped $6,000 (on a $14,000 contract) after the 60 day price guarantee on bids for this project expired as the plans had not yet been approved by the city. Unfortunately, this situation is being described to us as a jump in the price of copper, and after getting prices from three other electrical subcontractors, two of these new prices fall above the $20,000 mark (what the original subcontractor's price jumped to), and one falls less than $400 below it, which we do not consider a great enough difference to justify leaving the subcontractor who first won the project. I am still waiting to hear back from the general contractor about a discussion he was supposed to have with this original electrical subcontractor about a reduction in price.
I have talked to the owner a number of times this week. As the sprinkler contractor has gotten started, and will finish with the apartment portion of the work at the end of this week, he is understandably antsy about the general contractor starting work and about the $6,000 that is currently hanging in the balance price-wise on the electrical sub-contract. We were supposed to reach an agreement on the electrical subcontractor front by yesterday (Wednesday the 6th), but as of yet it remains unresolved. I plan to make calls about this tomorrow (Friday) morning.
On a separate note, I have received two calls this week about new projects. Neither is a "home-run project" but both represent work that we are perfectly capable of executing and billing for.
The first call, received on Monday, was from a gentleman who was interested in buying some house plans online and having us make some slight modifications to them before submitting them to the city for approval. This is not any designer's favorite thing to do, but it was apparent from talking to the gentleman that he was set on buying the "book plans" so we decided to accept the project on an hourly rate for changes. Changes made included widening the garage from 21 feet to 23 feet, and removing a covered porch from the plans. For this we billed 5 hours plus printing charges - a deal which was more than acceptable to the client.
The second call, received on Tuesday, was from a contractor who is working with a small private school in Fayetteville. This school has recently moved from a previous location to a new building in a commercial area of Fayetteville. More recently, they have expanded to include two prefab units - one small unit and one large one. After installing the units, an open deck was built between them. This deck is 11.5 feet wide, and meets a set of stairs on one side and a ramp on the other. The deck as described is built and in use, but the project as proposed to up will involve enclosing this deck and turning it into conditioned space. so that kids can move between the prefab units without getting cold or wet. This will be a tricky situation for a number of reasons. First, a 5 foot landing is required outside of the classroom door before the start of a ramp. Though the deck plans as shown to us were drawn correctly by their original designer, the deck was not built according to plans. Because of this, the landing outside of the units' door is not to code. Secondly, the foundation and structure of the deck are designed to support just that - a deck - so more structure will be needed to support walls and a roof, and it is not clear at this point whether the existing foundation will be sufficient.
Week of January 28 - February 01, 2013
This week was mostly concerned with assuring the owner that the project was moving forward whilst the contractor dealt with the previously described issue with the electrical subcontractor's price. It was determined that we would discuss the increase in price with the electrical subcontractor while looking for prices from other electrical subcontractors to compare. We agreed to try to make a decision by Wednesday February 06, 2013. The owner is understandably anxious to start the project, though he is not pleased at the thought of a $6,000 change order due to the increase in the electrical contractor's price. We do have, in the existing contract, a $5,000 miscellaneous allowance. All of part of this $5,000 sum may be used to cover this price increase if necessary, though if we use this entire allowance we leave ourselves more vulnerable to change orders further into the construction. We will follow up on this issue more in the coming week. The MEP Engineer has also taken time this week to look over the contract the owner signed with the Sprinkler Contractor, and has found it to be reasonably fair to both parties. As mentioned in last week's entry, he will be overseeing the installation of the sprinkler system through regular site visits, as I have not performed CA on a project with a sprinkler system up to this point.
Week of January 21 - January 25, 2013.
This week and the preceding week primarily revolved around a reacquainting myself with project developments in my absence and preparing for a pre-construction meeting for the Day Care Facility Renovation project on January 23. In preparation for the pre-construction meeting, I called the General Contractor, the Fire Sprinkler System Contractor, and the owner to arrange a time which would work for all parties. The owner was only available on Monday, Wednesday, and Friday, and given my schedule with school it was deemed that Wednesday morning would be most appropriate. The day before the meeting, I prepared notes for myself regarding topics to cover with all parties present and created a sign-up document, as well as making sure I had all of the most recent plan pages together in one set. The morning of the meeting I arrived early and spoke with the owner, then greeted the representatives from the GC and the Sprinkler Contractor as they arrived at the building. We went into an unused room with a table and chairs, signed the sign-up sheet with name and contact information, then proceeded to discuss the topics which I had written down in preparation for the meeting. These topics and the appropriate response are as follows:
Sign-up
_- Self-explanitory
Delay explanation
_- This project took an inexplicably long time to clear the planning and inspections department in the city, so this note just covers a general apology and explanation of the delays involved in that process.
Electrical re-bid
_- Because the permits were not approved by the city until more than 60 days after the bid date, the subcontractors were no longer legally bound to their prices. The electrical subcontractor's price increased $6,000 (from an original bid number of $14,000). This was left unexplained and was too radical a change to be attributed to material price fluctuation, so the GC decided (and rightfully so) to speak with other electrical subcontractors about pricing this job. During the meeting we were told that they would have prices from two other electrical subcontractors by the end of the next day.
Coordination between GC and Sprinkler Contractor
_- Because the owner on this project was trying to accomplish a lot on a shoestring budget, we decided to bid the sprinkler system (> 50% of the total project cost) separately from the rest of the renovation project. We feel that saved the owner a fair amount of money in eliminating a markup from the GC, but this means that the GC and the Sprinkler Contractor will need to coordinate without the Sprinkler Contractor being under the GC's contract with the owner. Coordination had been touched on in phone calls before this meeting, but having all parties present (including the owner, who is operating a day care facility in part of the building) was an essential part of this meeting. The representatives from the GC and Sprinkler Contractor were able to hash out what their level of time involvement would be in each quadrant of the building and determine with the help of the owner what the best schedule would be moving forward.
****************
Brief Project Description
This project is a renovation of a metal building erected in the early 1990s in Fayetteville, NC. This building is composed of four separate units, two each on two levels. The downstairs contains a child care facility and a newly vacant space which used to house offices for a home-care business. The upstairs contains a therapy center for developmentally handicapped children on one side and an apartment on the other. The premise of the project is combining the two sides of the building downstairs into one larger childcare facility. Because the building is 3/4 occupied, there will be some inherent "shuffling around" of the businesses in these spaces while the renovations occur. Because each unit is separated by a firewall and uses a separate HVAC system, this should not present too much of a problem. It was, however, very important to discuss "order-of-operations" with the owner, GC, and Sprinkler Contractor present so that all parties would be on the same page.
***************
Decorum on site
_- The next thing we discussed was decorum - a point that always comes up in pre-construction meetings, but one that is particularly important in this case, as there will be young children present on site. Representatives from the GC and Sprinkler Contractor were told that their workers on site follow the rules below:
--- Wear plain clothing with no profanity, inappropriate images, etc.
--- Absolutely no fraternization with children or employees on site.
--- No alcohol, tobacco, or drugs whatsoever on the site.
--- Keep messes contained and clean up immediately when work in an area is finished for the day, particularly in the apartment.
--- There are to be no felons among the workers for GC or subcontractors whatsoever. Not worth the risk on this project.
Parking
_- Because the facility's existing single-access paved lot will need to be cut just about down the middle for the installation of the new pipe for the sprinkler system. This means that parking will be tight during construction. As such, we ruled that there are to be no construction-related vehicles parked in the facility's paved lot. Luckily, the existing building is located on a large site, so space will not be an issue. It was determined that building staff would circle around the back of the building (grass/dirt) and park on the grass facing the paved lot. Construction vehicles will park behind the building in an open dirt area. This will free up 100% of the facility's paved surface parking for patrons of its businesses and the upstairs apartment tenant. Even with the reduction in available parking because of the required underground work, this remaining surface parking should be sufficient.
Lay-down space
_- At the time of this pre-construction meeting, the required supplies for the sprinkler system were already purchased and stored in a metal shipping container on-site at the rear of the building in an open dirt area. Any additional required material storage should be in the immediate vicinity of this container. This open dirt area at the back of the site is the same area where construction vehicle parking is set to be. Space should not be an issue.
Environmental safety
_- Each of the four units in this building have a separate HVAC system, so environmental contamination should not be a difficult issue to solve. The contractors have been instructed to cover any openings between units with sheet plastic, and to turn the HVAC system in the unit they are working in off completely while cutting drywall or otherwise creating dust. They have also been instructed to place an additional filter over any return air duct for the duration of construction. Any mess from dust is to be cleaned up at the end of the work day.
General safety and insurance
All OSHA and State regulations are to be followed in the execution of the work. Before work is started, both the GC and the Sprinkler Contractor are to submit documentation of their Liability Insurance and Worker's Comp.
Interruption of work
It will be beneficial to all parties involved if work is scheduled in such a way that it is continuous from start to finish. That is, no delays for materials, subcontractors, waiting for another party to finish work etc. After discussing coordination, we do not expect this to be an issue.
Coordination
This topic was the lengthiest discussion at the meeting, and perhaps the most important as well. The owner, the General Contractor, and the Sprinkler contractor participated in a discussion involving their needs in terms of time and space for the project. Based on this discussion, we are scheduling construction so that it has minimal impact on the building owner's operations. As a part of this, the contractors will be required to give at least 48hrs notice to the owner when they are close to completing one quadrant of the building and preparing to move on to the next.
Regular meetings and site visits
_- It was decided that the day of the month and time used for the pre-construction meeting would be acceptable to all parties for use in subsequent progress meetings. This means that progress meetings will be held on the third Wednesday of the month at 10:00am. Site visits will occur at random based on updates from the contractor about current operations. The MEP Engineer will also be making site visits to check on the installation of the sprinkler system.
Site walkaround
_- Only two small issues were raised during a walkaround of the site at the close of the meeting. First, we instructed the sprinkler contractor to tell his underground subcontractor that he should extend his cut through the parking lot asphalt one foot laterally beyond where it is marked to coincide with an existing asphalt change from where the parking lot was previously extended. This should help with a cleaner appearance. Secondly, we asked the general contractor to reattach a loose piece of metal siding at the side of the building at some point during construction work. The general contractor agreed to take care of this issue.
Overall I feel that the meeting went quite well and accomplished what it needed to in terms of getting the owner, architect, general contractor and sprinkler contractor on the same page in terms of scheduling and procedure.
Sign-up
_- Self-explanitory
Delay explanation
_- This project took an inexplicably long time to clear the planning and inspections department in the city, so this note just covers a general apology and explanation of the delays involved in that process.
Electrical re-bid
_- Because the permits were not approved by the city until more than 60 days after the bid date, the subcontractors were no longer legally bound to their prices. The electrical subcontractor's price increased $6,000 (from an original bid number of $14,000). This was left unexplained and was too radical a change to be attributed to material price fluctuation, so the GC decided (and rightfully so) to speak with other electrical subcontractors about pricing this job. During the meeting we were told that they would have prices from two other electrical subcontractors by the end of the next day.
Coordination between GC and Sprinkler Contractor
_- Because the owner on this project was trying to accomplish a lot on a shoestring budget, we decided to bid the sprinkler system (> 50% of the total project cost) separately from the rest of the renovation project. We feel that saved the owner a fair amount of money in eliminating a markup from the GC, but this means that the GC and the Sprinkler Contractor will need to coordinate without the Sprinkler Contractor being under the GC's contract with the owner. Coordination had been touched on in phone calls before this meeting, but having all parties present (including the owner, who is operating a day care facility in part of the building) was an essential part of this meeting. The representatives from the GC and Sprinkler Contractor were able to hash out what their level of time involvement would be in each quadrant of the building and determine with the help of the owner what the best schedule would be moving forward.
****************
Brief Project Description
This project is a renovation of a metal building erected in the early 1990s in Fayetteville, NC. This building is composed of four separate units, two each on two levels. The downstairs contains a child care facility and a newly vacant space which used to house offices for a home-care business. The upstairs contains a therapy center for developmentally handicapped children on one side and an apartment on the other. The premise of the project is combining the two sides of the building downstairs into one larger childcare facility. Because the building is 3/4 occupied, there will be some inherent "shuffling around" of the businesses in these spaces while the renovations occur. Because each unit is separated by a firewall and uses a separate HVAC system, this should not present too much of a problem. It was, however, very important to discuss "order-of-operations" with the owner, GC, and Sprinkler Contractor present so that all parties would be on the same page.
***************
Decorum on site
_- The next thing we discussed was decorum - a point that always comes up in pre-construction meetings, but one that is particularly important in this case, as there will be young children present on site. Representatives from the GC and Sprinkler Contractor were told that their workers on site follow the rules below:
--- Wear plain clothing with no profanity, inappropriate images, etc.
--- Absolutely no fraternization with children or employees on site.
--- No alcohol, tobacco, or drugs whatsoever on the site.
--- Keep messes contained and clean up immediately when work in an area is finished for the day, particularly in the apartment.
--- There are to be no felons among the workers for GC or subcontractors whatsoever. Not worth the risk on this project.
Parking
_- Because the facility's existing single-access paved lot will need to be cut just about down the middle for the installation of the new pipe for the sprinkler system. This means that parking will be tight during construction. As such, we ruled that there are to be no construction-related vehicles parked in the facility's paved lot. Luckily, the existing building is located on a large site, so space will not be an issue. It was determined that building staff would circle around the back of the building (grass/dirt) and park on the grass facing the paved lot. Construction vehicles will park behind the building in an open dirt area. This will free up 100% of the facility's paved surface parking for patrons of its businesses and the upstairs apartment tenant. Even with the reduction in available parking because of the required underground work, this remaining surface parking should be sufficient.
Lay-down space
_- At the time of this pre-construction meeting, the required supplies for the sprinkler system were already purchased and stored in a metal shipping container on-site at the rear of the building in an open dirt area. Any additional required material storage should be in the immediate vicinity of this container. This open dirt area at the back of the site is the same area where construction vehicle parking is set to be. Space should not be an issue.
Environmental safety
_- Each of the four units in this building have a separate HVAC system, so environmental contamination should not be a difficult issue to solve. The contractors have been instructed to cover any openings between units with sheet plastic, and to turn the HVAC system in the unit they are working in off completely while cutting drywall or otherwise creating dust. They have also been instructed to place an additional filter over any return air duct for the duration of construction. Any mess from dust is to be cleaned up at the end of the work day.
General safety and insurance
All OSHA and State regulations are to be followed in the execution of the work. Before work is started, both the GC and the Sprinkler Contractor are to submit documentation of their Liability Insurance and Worker's Comp.
Interruption of work
It will be beneficial to all parties involved if work is scheduled in such a way that it is continuous from start to finish. That is, no delays for materials, subcontractors, waiting for another party to finish work etc. After discussing coordination, we do not expect this to be an issue.
Coordination
This topic was the lengthiest discussion at the meeting, and perhaps the most important as well. The owner, the General Contractor, and the Sprinkler contractor participated in a discussion involving their needs in terms of time and space for the project. Based on this discussion, we are scheduling construction so that it has minimal impact on the building owner's operations. As a part of this, the contractors will be required to give at least 48hrs notice to the owner when they are close to completing one quadrant of the building and preparing to move on to the next.
Regular meetings and site visits
_- It was decided that the day of the month and time used for the pre-construction meeting would be acceptable to all parties for use in subsequent progress meetings. This means that progress meetings will be held on the third Wednesday of the month at 10:00am. Site visits will occur at random based on updates from the contractor about current operations. The MEP Engineer will also be making site visits to check on the installation of the sprinkler system.
Site walkaround
_- Only two small issues were raised during a walkaround of the site at the close of the meeting. First, we instructed the sprinkler contractor to tell his underground subcontractor that he should extend his cut through the parking lot asphalt one foot laterally beyond where it is marked to coincide with an existing asphalt change from where the parking lot was previously extended. This should help with a cleaner appearance. Secondly, we asked the general contractor to reattach a loose piece of metal siding at the side of the building at some point during construction work. The general contractor agreed to take care of this issue.
Overall I feel that the meeting went quite well and accomplished what it needed to in terms of getting the owner, architect, general contractor and sprinkler contractor on the same page in terms of scheduling and procedure.